Set up a coordination meeting between, Engineering, Sales, and Electrical. Review all aspects of job including budget, equipment specifications, site layout and access needs, timing and required personnel.
Order long lead time components with Sales approval.
Coordinate a site survey to verify building dimensions, area access, and customer requirements
Order remaining components based on input from Electrical department , Engineering, and fabrication drawings
Fill out and provide electrical with crane build sheets from the project management form
Schedule fabrication and installation with the corresponding fabrication and install managers based on ship dates from component order acknowledgements, and customer timeline requirements
All project documentation including quotes, POs , Order Acknowledgements, and signed drawings shall be kept in the project file either on the All drive or in CRM